Published by FEWE February 24th, 2009
in Lighthouse Project.
The aim of the task is retrofitting of ventilation and air conditioning system in existing education purpose building “B” of the Police Academy in Katowice with installing of a Ground Heat Exchanger (GHE) with capacity 10 000 m3/h. GHE will be working for the purposes of the ventilation and the air conditioning in the building that has the area of about 2485 m2 and cubic capacity 8975 m3.
An additional purpose is a greenhouse gas emission reduction and decrease of consumption and costs of thermal energy for heating in winter and electricity for the purposes of the air-conditioning of rooms in summer.
The realization of the project is a result of the „Program of Complete Thermal modernization of Buildings of the Police Academy in Katowice” implemented by the investor.

Published by SEC January 30th, 2009
in Lighthouse Project.
The project aims at major reconstruction with adding additional habitable space of Kindergarten No 165, named “Latinka”, in Iztok Quarter, Sofia. It’s at design stage with planned start of works mid. 2009.

Published by GERTEC January 20th, 2009
in Lighthouse Project.
Two floors of the office building with a total net area of 1.100 m2 and a volume of 3.100 m3 are used by a software house with high heat loads due to their office equipment. In all, there are five floors with 600 m2 glazed surface. The specific cooling load is 50 W/m2.

Published by ESV January 19th, 2009
in Lighthouse Project.
By 2030, 100% of Upper Austria’s electricity and space heating energy consumption should be produced with renewable energy sources. To reach this goal, it is necessary to reduce the demand for space heating and electricity considerably. Lighthouse projects like the retirement and nursing home in Wels play an important role in this. Through visionary technologies, the standard of tomorrow is already shown today.
The ground-breaking ceremony for the retirement and nursing home Wels Vogelweide took place in June 2008, the home will prospectively be ready to move into in March 2010. All in all, it comprises 124 rooms and achieves an energy performance indicator of 7.4 kilowatt-hours per square meter and year. Originally, an energy per-formance indicator of 24 kWh/m²a was envisaged. Through the comprehensive project assistance of the O.Ö. Energiesparverband various measures and optimisations were put in place which resulted in the building reaching the passive building standard.